Marion St after reconstruction work
Location
Work was carried out on the northern side of Marion St between Meredith St and Chapel Rd.
Scope
• Reconstruction of stormwater drainage structures and installation of stormwater pipes.
• Reconstruction of kerb & gutter sections and vehicular crossings
• Reconstruction of concrete footpath slabs at various locations
• Road resurfacing
Timing
The work commenced in mid March 2012 and was completed in May 2012.